Carts Corporation is trying to determine how long it takes for one product to pass through the production process. The following information was gathered regarding

Carts Corporation is trying to determine how long it takes for one product to pass through the production process. The following information was gathered regarding how many days the product spent in various production activities.

Activity Number of Days
Inspection 5
Storage 6
Assembly 3
Handling 2
Painting 2
Packaging 1

a. Which of the above activities are value-added?

b. What is Carts total cycle time?

c. Determine Carts manufacturing efficiency ratio.

d-1. If Carts implements a total quality management program and a just-in-time inventory system, which of these activities could be eliminated?

d-2. If Carts implements a total quality management program and a just-in-time inventory system, what would be the change in Carts manufacturing efficiency ratio?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Auditing

Authors: Hall, J Scott Harr

3rd Edition

1133008046, 978-1439079119

More Books

Students also viewed these Accounting questions

Question

What capital assets (if any) of ONNOs need not be depreciated?

Answered: 1 week ago

Question

Why is job analysis considered to be a basic HR tool?

Answered: 1 week ago

Question

5.1 Define recruitment and describe the recruitment process.

Answered: 1 week ago