Question
Carts Corporation is trying to determine how long it takes for one product to pass through the production process. The following information was gathered regarding
Carts Corporation is trying to determine how long it takes for one product to pass through the production process. The following information was gathered regarding how many days the product spent in various production activities.
Activity | Number of Days |
Inspection | 5 |
Storage | 6 |
Assembly | 3 |
Handling | 2 |
Painting | 2 |
Packaging | 1 |
a. Which of the above activities are value-added?
b. What is Carts total cycle time?
c. Determine Carts manufacturing efficiency ratio.
d-1. If Carts implements a total quality management program and a just-in-time inventory system, which of these activities could be eliminated?
d-2. If Carts implements a total quality management program and a just-in-time inventory system, what would be the change in Carts manufacturing efficiency ratio?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started