Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

CASE 11 Tom Tarl obtains a contract with the Burquitlam Shopping Centre on April 7, to pave the parking lot by May 15 for $45

CASE 11

Tom Tarl obtains a contract with the Burquitlam Shopping Centre on April 7, to pave the parking lot by May 15 for $45 000. Tarl then enters into a written contract with Frank Fether on April 9 to pave Fether's driveway by May 20 for $3 000. On April 21, Tarl's employee Hank becomes ill. Without Hank's help, Tarl feels that he will not be able to complete both the Burquitlam contract and the Fether contract on time. Tarl calls Fether to tell him that the contract is off. Fether agrees. The next morning, Hank makes a remarkable recovery from his illness, and he is back at work by that afternoon. Tarl realizes that he can now finish both contracts on time. He calls Fether to affirm that he will be able to pave his driveway after all. Fether tells Tarl that his services are no longer required.Tarl reminds Fether of the written agreement and insists that he honour the agreement. Fether refuses.

Parties

Issue

Analysis

Remedy

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Law Of Contract

Authors: Paul Richards

14th Edition

1292251484, 978-1292251486

More Books

Students also viewed these Law questions

Question

work settings of recent graduates;

Answered: 1 week ago

Question

Mortality rate

Answered: 1 week ago

Question

Armed conflicts.

Answered: 1 week ago