Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Case #6 Mellon and Tufts Construction are two general contracting firm and developers which have successfully completed several projects together and have an established working

Case #6

Mellon and Tufts Construction are two general contracting firm and developers which have successfully completed several projects together and have an established working relationship. All contracts between the two have been negotiated guaranteed maximum price contracts. Change orders on past projects have been minimal, and the general contractor has always been willing and able to use project savings to compensate for minor cost increases. Instead of adding more estimated dollars to the GMP for change orders, the GC has absorbed the cost of the extras from their in-house buyout fund, which generally would have been submitted for a split at the end of the project.

On the last project, the GC was able to move 30% of the value of savings used to cover change orders, which was their portion of the savings split, into their fixed fee during the course of construction, rather than waiting for the end of the project. Both parties benefited from this arrangement.

Their current project is a $40 million office building that is halfway through the overall schedule and is near completion of the structural work, which is where most of the GC's labor risk is. There have been a large number of agreed upon (i.e. not disputed) change order proposals (COPs) for added scope and document discrepancies equaling approximately $600,000. It is still relatively early in the project, and the project manager is confident that this time there will not be enough savings to compensate for all of these changes. The project manager (PM) has kept the developer notified of changes by submitting COPs for the work and sharing his change order log. The developer has given the GC verbal direction to proceed with the changes but refuses to sign the COPs until the GC can present savings as on previous projects. The PM documents these directions in his weekly meeting notes. Now, with all of the subcontractors securely bought out and most of the estimating risk behind him, the project manager is expecting only approximately $200,000 in savings but remains reluctant to release it until the building is weathertight.

Questions:

(NOTE: Explain Your Answers in Detail.

Think Outside the box i.e. subsequent damages, countersuits)Use legal terminology and case law citations as much as possible. Please provide an example of a connection to textbook case with citation

  • Take the position of the general contractor. Assume that the GC considers the developer a key client and does not want to jeopardize their relationship. What should the project manager do? Should the general contractor absorb all of the COPs as before? Discuss in detail the legal concern.
  • Take the position of the developer. Can you contractually proceed in this fashion? How do you defend your position? What are the legal issues here?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Criminal Law Text Cases And Materials

Authors: Jonathan Herring

9th Edition

0198848471, 978-0198848479

More Books

Students also viewed these Law questions

Question

What is the difference between an ADT and a data structure?

Answered: 1 week ago