Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Case No. 101 DAMAGES FOR SUBSTANTIAL PERFORMANCE IN A CONSTRUCTION CONTRACT/ECONOMIC WASTE Jacob & Youngs. Inc. Y. Kent Court of Appeals 230 N.Y. 239, 129
Case No. 101 DAMAGES FOR SUBSTANTIAL PERFORMANCE IN A CONSTRUCTION CONTRACT/ECONOMIC WASTE Jacob & Youngs. Inc. Y. Kent Court of Appeals 230 N.Y. 239, 129 NJE. 889 (1921) FACTS: Plaintiff Jacob & Youngs, Inc. (Jacob) contracted to build a home for defendant George E. Kent (Kent) for approximately $77,000.00. One of the plumbing specifications in the contract required that the pipe be of the grade known as "standard pipe of Reading manufacture." In March 1915, Kent learned that some of the pipe was not Reading but instead was made by other manufacturers. Kent demanded that the pipe be replaced to conform to contract specifications. Some of the pipe was exposed and accessible in the basement but most of it was encased in the walls and thus not reasonably accessible. Replacement of the pipe would therefore have required demolition of various parts of the structure at considerable expense. Jacob did not replace the pipe and in this action sought to recover the unpaid balance of the contract price, $3,483.46. Jacob was able to demonstrate that its use of the wrong pipe was neither willful nor fraudulent but rather was the result of an oversight. Additionally Jacob proved that no difference existed in quality, appearance, and market value between the Reading brand specified in the contract and the brands that were installed. ISSUE: Where a contractor completes the building of a home but deviates from the contract requirements, albeit in an insignificant way, and the cost to correct the work so that it conforms with the contract would be substantial, is the measure of damages the cost to correct the work so that it conforms with the contract requirements or the difference in value? DECISION: The difference in value; judgment for Jacob. REASONING: When a contractor deviates from the required performance yet substantially performs, the contractor is entitled to the contract price less damages for the improper performance. The usual measure of damages is the cost of completion. If. however. the cost of completion would result in economic waste, that is, the benefit gained would be slight compared to the cost, the proper measure of damages is the difference in value of the building as constructed and the value if the building had been built consistent with contract specifications. In this case Jacob had substantially performed. To require Jacob to demolish substantial paris of the structure in order to replace pipe with new pipe of the same general quality would far exceed the value, if any, added to the structure and thus would constitute economic waste. The amount of damages in this case measured by the difference in value " would be either nominal or nothing. * * * QUESTION * * s See back of text for answer) was the cost of completion not the appropriate measure of damages in this case
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started