Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Case Study - Ducor Chemical Ducor Chemical received a research and development (R&D) contract from one of its most important clients. The client had awarded

Case Study  - Ducor Chemical
Ducor Chemical received a research and development (R&D) contract from one of its
most important clients. The client had awarded Ducor a 12-month, sole-source contract
for the R&D effort to create a new chemical that the client required for one of its future
products. If Ducor could develop the product, the long-term production contract that
would follow could generate significant profits over the next several years.
In addition to various lab personnel who would be used as needed, the contract
mandated that a senior chemist be assigned for the duration of the project. In the past,
senior chemists had been used mainly for internal rather than external customer
projects. This would be the first time a senior chemist had been assigned to this client.
With only four senior chemists on staff, the project manager expected the resource
negotiation process with the lab manager to be an easy undertaking.
Project manager: ") understand you've already looked over the technical requirements,
so you should understand the necessity for assigning your best senior scientist."
Lab manager: "All of my senior scientists are good. Any one of them can do the job.
Based on the timing of your project, I have decided to assign John Thornton.
Project manager:
"Just my luck! You assigned the only one I cannot work with
effectively. I have had the misfortune of working with him before. He's extremely
arrogant and unpleasant to work with."
Lab manager: "Perhaps so, but he got the job done, didn'the?"
Project manager: "Yes, he did. Technically, he is capable. However, his arrogant
attitude and sarcasm produced a demoralizing atmosphere for my team. That project
was about three months in length. This project is at least a year. Also, if follow-on work
is generated, as I expect it to be, I'll be stuck with him for a long time. That's
unacceptable to me.
Lab manager: "lIl talk to John and see if I can put a gag in his mouth. Anyway, you're a
good project manager and you should know how to work with these technical and
scientific prima donnas."
Project manager: "I'll never be able to maintain my sanity having to work with him full
time for at least one year. Surely you can assign one of the other three senior chemists
instead.
Lab manager: "Because of the nature of the other projects I have, John is the only
senior chemist I can release for one full year. If your project were two or three months,
then I might be able to give you one of the other senior chemists."
Project manager: "I feel like you are dumping Thornton on me without considering what
is in the best interests of the project. Perhaps we should have the sponsor resolve this
conflict."
Lab manager: "First of all, this is not a conflict. Second, threatening me with sponsor
intervention will not help your case. Do you plan on asking for my resources or support
ever again in the future? I'm like an elephant. I have a long memory. Third, my
responsibility is to meet your deliverable in a manner that is
in the best interest of the company. "Try to look at resource assignments through my
eyes. You're worried about the best interests of your project. I have to support some 20
projects and must make decisions in the best interests of the entire company. Benefiting
one project at the expense of several other projects is not a good company decision.
And 1 am paid to make sound company decisions, whereas you are paid to make a
project decision "
Project manager: "My salary, promotion, and future opportunities rest solely on the
success of this one project, not20."
Lab manager:
"Our relationship must be a partnership based on trust if project
management is to succeed. You must trust me when I tell you that your deliverables will
be accomplished within time, cost, and quality. It's my job to make that promise and to
see that it is kept.
Project manager: "But what about morale? That should also be a factor. There is also
another important consideration. The customer wants monthly team meetings, at our
location, to assess progress."
Lab manager: "I know that. I read the requirements document. Why are the monthly
meetings a problem?"
Project manager: "I have worked with this customer before. At the team meetings, they
want to hear the technical status from the people doing the work rather than from the
project manager. That means that John Thornton would be directly interfacing with the
customer at least once a month. Thornton is a loose
cannon, and there's no telling what words will come out of his mouth. If it were not for
the interface meetings, I might be agreeable to accept Thornton. But based on previous
experience, he simply does not know when to shut up! He could cause irrevocable
damage to our project.
Lab manager: "I will take care of John Thornton. And to appease you, I will also attend
each one of the customer interface meetings to keep Thornton in line. As far as I'm
concerned, Thornton will be assigned and the subject is officially closed!'
The project continued.
John Thornton was assigned to the project team. During the second interface meeting,
Thornton stood up and complained to the customer that some of the tests that the customer had requested were worthless, serving no viable purpose. Furthermore,
Thornton asserted that if he were left alone, he could develop a product far superior to
what the customer had requested.
The customer was furious over Thornton's remarks and asserted that they would now
evaluate the project performance to date as well as Ducor's commitment to the project.
After the evaluation, they would consider whether the project should be terminated or
perhaps assigned to one of Ducor's competitors. The lab manager had not been
present during either of the first two customer interface meetings.
QUESTIONS
6. How do we create a partnership between the project manager and line man agers
when the project manager focuses only on the best interest of his or her project
and the line manager is expected to make impartial company decisions?
7. Who should have more of a say during negotiations for resources: the project
manager or the line manager?
8. How should irresolvable conflicts over staffing between project and line
managers be handled?
9. Should an external customer have a say in project staffing?
10.How do we remove an employee who is not performing as expected?
11. How would you have handled the situation right from the beginning?
12. Should project managers negotiate for people or deliverables?

Step by Step Solution

3.38 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

1 How do we create a partnership between the project manager and line managers when project manager focus only on the best interest of his or her project and the line manager is expected to make impar... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Management Science

Authors: Bernard W. Taylor

11th Edition

132751917, 978-0132751919

More Books

Students also viewed these Accounting questions