Question
Cash Flow For the project whose cost data are given below, plot the cumulative project expenditures, value of work, and progress payments received versus time.
Cash Flow
For the project whose cost data are given below, plot the cumulative project expenditures, value of work, and progress payments received versus time. What is the contractor's maximum negative cash flow, and when, does it occur? Progress payments are calculated at the end of each month and received the middle of the following month. Retainage is 10% until project completion. Assume that final project payment, including released retainage, is received the middle of the month following project completion.
End-of-Month Cumulative Values Month Expenditures Value of Work
1 $12,000 $8,000
2 24,000 20,000
3 41,000 38,000
4 60,000 58,000
5 85,000 84,000
6 120,000 120,000
7 175,000 180,000
8 230,000 240,000
9 240,000 250,000
10 245,000 260,000
11 246,000 268,000
12 247,000 275,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started