Question

1 Approved Answer

Cash Flow For the project whose cost data are given below, plot the cumulative project expenditures, value of work, and progress payments received versus time.

Cash Flow

For the project whose cost data are given below, plot the cumulative project expenditures, value of work, and progress payments received versus time. What is the contractor's maximum negative cash flow, and when, does it occur? Progress payments are calculated at the end of each month and received the middle of the following month. Retainage is 10% until project completion. Assume that final project payment, including released retainage, is received the middle of the month following project completion.

End-of-Month Cumulative Values Month Expenditures Value of Work

1 $12,000 $8,000

2 24,000 20,000

3 41,000 38,000

4 60,000 58,000

5 85,000 84,000

6 120,000 120,000

7 175,000 180,000

8 230,000 240,000

9 240,000 250,000

10 245,000 260,000

11 246,000 268,000

12 247,000 275,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Finance Exchange Rates And Financial Flows In The International Financial System

Authors: Heather D. Gibson

1st Edition

0582218128, 978-0582218123

More Books

Students also viewed these Finance questions