Cash flow to the firm (FCFF) is provided below. What is the NPV of this project? Chose the appropriate rate to compute the NPV. Cost
Cash flow to the firm (FCFF) is provided below. What is the NPV of this project? Chose the appropriate rate to compute the NPV. Cost of capital is 12% and cost of equity is 14%.
Year | 0 | 1 | 2 | 3 | 4 |
cf | -100 | 75 | 85 | 95 | 105 |
A) 157
B) 148
C) 169