Cash Payback Period, Net Present Value Method, and Analysis Elite Apparel Inc. is considering two investment projects. The estimated net cash flows from each project

Cash Payback Period, Net Present Value Method, and Analysis

Elite Apparel Inc. is considering two investment projects. The estimated net cash flows from each project are as follows:

Year Plant Expansion Retail Store Expansion
1 $101,000 $85,000
2 83,000 99,000
3 71,000 68,000
4 65,000 48,000
5 20,000 40,000
Total $340,000 $340,000

Each project requires an investment of $184,000. A rate of 15% has been selected for the net present value analysis.

Present Value of $1 at Compound Interest
Year 6% 10% 12% 15% 20%
1 0.943 0.909 0.893 0.870 0.833
2 0.890 0.826 0.797 0.756 0.694
3 0.840 0.751 0.712 0.658 0.579
4 0.792 0.683 0.636 0.572 0.482
5 0.747 0.621 0.567 0.497 0.402
6 0.705 0.564 0.507 0.432 0.335
7 0.665 0.513 0.452 0.376 0.279
8 0.627 0.467 0.404 0.327 0.233
9 0.592 0.424 0.361 0.284 0.194
10 0.558 0.386 0.322 0.247 0.162

Required:

1a. Compute the cash payback period for each project.

1b. Compute the net present value. Use the present value of $1 table above. If required, round to the nearest dollar.

image text in transcribedimage text in transcribed

Chapter 26 Homework eBook Print Item Cash Payback Period, Net Present Value Method, and Analysis Elite Apparel Inc. is considering two investment projects. The estimated net cash flows from each project are as follows: Year Plant Expansion Retail Store Expansion 1 $101,000 $85,000 2 83,000 99,000 3 71,000 68,000 4 65,000 48,000 5 20,000 40,000 Total $340,000 $340,000 Each project requires an investment of $184,000. A rate of 15% has been selected for the net present value analysis. Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 0.890 0.826 0.797 0.756 0.694 3 0.840 0.751 0.712 0.658 0.579 4 0.792 0.683 0.636 0.572 0.482 5 0.747 0.621 0.567 0.497 0.402 6 0.705 0.564 0.507 0.432 0.335 eBook Print Item Chapter 26 Homework 3 0.840 0.751 0.712 0.658 0.579 4 0.792 0.683 0.636 0.572 0.482 5 0.747 0.621 0.567 0.497 0.402 6 0.705 0.564 0.507 0.432 0.335 7 0.665 0.513 0.452 0.376 0.279 8 0.627 0.467 0.404 0.327 0.233 9 0.592 0.424 0.361 0.284 0.194 10 0.558 0.386 0.322 0.247 0.162 Required: 1a. Compute the cash payback period for each project. Cash Payback Period Plant Expansion 2 years Retail Store Expansion 2 years 1b. Compute the net present value. Use the present value of $1 table above. If required, round to the nearest dollar. Plant Expansion Retail Store Expansion Total present value of net cash flow Less amount to be invested Net present value 2. Because of the timing of the receipt of the net cash flows, the plant expansion offers a higher net present value

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting Theory And Practice

Authors: R. Palaniappan, N. Hariharan

1st Edition

9380578342, 978-9380578347

More Books

Students also viewed these Accounting questions