Question 1 A residential client hired a general contractor (GC) to construct a major $3 million executive home. The client contracted separately with a

Question 1 A residential client hired a general contractor ( (mathrm{GC}) ) to construct a major ( $ 3 ) million execut 

Question 1 A residential client hired a general contractor (GC) to construct a major $3 million executive home. The client contracted separately with a reputable architect for the design. After the permit was obtained, the architect's contract was closed out. During the course of construction, the owner and the city had requested several changes, but none of them were formalized into the contract. Many of these were additive but some were also deductive changes. Many of the changes were due to building code changes. Because the general contractor understood this to be a time and materials (T&M) project, they had not felt it was necessary to submit change orders against a "budgeted" amount. The GC had previously invoiced and received 67% of the original budget, or $2 million, from the owner. These invoices were all reviewed and approved by the lender. At approximately 90% completion, the GC invoiced the owner for the full 100% amount of the original $3 million estimate. When pressed, the GC indicated that the project will overrun the budget by approximately $500,000. The owner and the GC disagree. The owner refuses to approve the current pay request. Can he do that? The GC pulls off the job and refuses to do any more work until the owner agrees to the revised budget of $3.5 million and pays the $1 million now due. Can the contractor legally do that? The owner dismisses the GC at this point. Both parties sue each other. How did this happen? Who is at fault? What should have been done to prevent this situation? What do they do now? You need to discuss this point at least by 200words. Give appropriate reference and citation for citation for your answer. (25 Marks)

Step by Step Solution

3.36 Rating (180 Votes )

There are 3 Steps involved in it

Step: 1

Question 1 The owner and the GC disagree The owner refuses to approve the current pay request Can he do that The owner has the right to refuse the current pay request from the GC if they disagree If t... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Using Financial Accounting Information The Alternative to Debits and Credits

Authors: Gary A. Porter, Curtis L. Norton

7th Edition

978-0-538-4527, 0-538-45274-9, 978-1133161646

More Books

Students also viewed these Accounting questions

Question

What does it mean to say that price elasticity of demand is 1.22?

Answered: 1 week ago

Question

1. Offer surprise rewards for good participation in class.

Answered: 1 week ago