CAT 1 AND 2 ATTEMPT ALL THE QUESTIONS (1 ) As cost accountant of Rackets Ltd, you estimate the standard cost of making one unit
CAT 1 AND 2
ATTEMPT ALL THE QUESTIONS
(1 ) As cost accountant of Rackets Ltd, you estimate the standard cost of making one unit is as follows:
Direct material 4 kilos at 7 per kilo
Direct wages 5 hours at 10 per hour
The actual cost of a batch of 1000 units was:
Direct material 28960 (4328 kilos)
Direct wages 50200 (5370 hours)
Calculate the following:
(i) The material price variance
(ii) The material usage variance
(iii) The total material cost variance
(iv) The labour rate variance
(v) The labour efficiency variance
(vi) The total labour cost variance
(vii) The total cost variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started