Question
Fogerty Company makes two productstitanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.70 19,000 units Sprockets
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit | Annual Production | ||
Hubs | 0.70 | 19,000 | units |
Sprockets | 0.30 | 44,000 | units |
Additional information about the company follows:
Hubs require $34 in direct materials per unit, and Sprockets require $18.
The direct labor wage rate is $14 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
Estimated | Activity | ||||
Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 22,230 | 130 | 104 | 234 |
Special processing (machine-hours) | $ | 166,500 | 3,700 | 0 | 3,700 |
General factory (organization-sustaining) | $ | 224,500 | NA | NA | NA |
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Step by Step Solution
3.33 Rating (168 Votes )
There are 3 Steps involved in it
Step: 1
1 Activity Cost Pool Overhead cost Total cost drivers Activity Rate ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started