CE 6 0 6 3 1 - Feasibility Study Design and Estimate Page limit: 1 0 pages for the body of the report. However, you
CE Feasibility Study Design and Estimate
Page limit: pages for the body of the report. However, you may include additional pages as an
appendix, ie the design layout of each of the alternatives.
Feasibility Estimate Assignment
An important developer client calls you on the phone and asks you to do a feasibility estimate to
evaluate financial feasibility of a development project that she has in mind. She owns the two pieces
of property in downtown South Bend shown below. She plans to develop both pieces of property into
paid parking facilities. One will be a longterm lease facility for commuters and the other will be an
hourly facility for noncommuters. The hourly facility will require an attendant to be onsite from
:AM to :PM and will include a small convenience store which per city code must have free off
street parking.
NOTRE DAME STREET
She intends to build a multistory parking structure on one lot and a surface level parking lot on the other.
She needs your help investigating two alternatives:
Alternative :
a A single parking structure that can park at least cars ON ONE OF THE LOTS. The code limits
these facilities to stories and must meet the dimensions specified in the South Bend Parking Code
including provision of handicapped parking stalls. The expected monthly rental rate is $onttall.
A consultant advised her that the vacancy rate for this usage is approximately
PLUS
b A single story wood frame with brick veneer convenience store building with a hour rated safe ON
THE OTHER LOT. The store would be about and generate $ month in net aftertax
revenue including the cost of the attendant who doubles as the parking lot attendant. The remainder of
the property would be fenced for a commercial hourly parking lot with an average hour vacancyrate of Spaces rent for $ hour for each space. The offstreet parking for the store and the
hourly parking lot must also meet the dimensions specified in the South Bend Parking Code including
provision of handicapped parking stalls.
Alternative :
Alternative with the store being replaced with a small building with a restroom for the parking
lot attendant. The building should be big enough for a doublepedestal desk, a filing cabinet and a
chair plus a toilet and sink in the restroom. The restroom should be accessible from the outside by
the users of the parking lot. It should be heated and airconditioned. Alternative revenues would
solely be from short and longterm parking. The cost for attendants is $onth.
Planned Design Approach:
The store building's front will utilize storefront glass door and window panels and any
exterior wall surface that does not face the alley must be covered with brick veneer.
Access to the alley is available for Lot if needed to optimize traffic flow in and out of the
hourly parking facility. The convenience store must front Notre Dame Street. Lot B cannot
use the alley for either entry or exit.
The City requires a parking structure design where the entry point is located at least feet
away from an intersection of city streets and an exit point must be greater than feet from
any intersection. Entry or exit from an alley is not restricted.
Building Code Design Constraints
Buildings:
The city has setback requirements and requires onproperty, offstreet parking space based on the gross
floor space in the building in accordance with South Bend Code attached
Offstreet parking must enter and exit at a point that is at least feet from the intersection of city streets.
Parking Structures:
Comply with the Americans with Disabilities Act... ie elevators, ramps, designated parking, widths of
sidewalks and pedestrian lanes inside the structure.
Minimum of two stairwells in the structure.
Lighted at all times
Security cameras recorded and monitored hours per day
Emergency public telephone on each floor.
Commercial Surface Level Parking Lots:
One foot high street light per every square feet of pavement.
Access into and out of the lot must be from the street.
The entire lot will be surrounded by an foot chain link fence with at least two gates. The fence must be
set back from the alley and street by feet and from the sides by feet.
Any other information that you believe you need to complete this study will not be forthcoming.
Therefore, make the appropriate assumptions and document them in your report. Complete a feasibility
estimate rough order of magnitude for each alternative. She wants to make sure that her
benefits are greater than her costs on an annual basis. Her required rate of return on the capital investment
is
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started