chap 16 - Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the

chap 16 - Entries and Schedules for Unfinished Jobs and Completed Jobs

Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations:

  1. Materials purchased on account, $3,190.
  2. Materials requisitioned and factory labor used:
    Job No. Materials Factory Labor
    101 $3,150 $3,050
    102 3,840 4,120
    103 2,550 2,010
    104 8,630 7,560
    105 5,480 5,760
    106 4,000 3,660
    For general factory use 1,070 4,510
  3. Factory overhead costs incurred on account, $6,020.
  4. Depreciation of machinery and equipment, $2,170.
  5. The factory overhead rate is $55 per machine hour. Machine hours used:
    Job No. Machine Hours
    101 16
    102 27
    103 15
    104 78
    105 27
    106 17
    Total 180
  6. Jobs completed: 101, 102, 103, and 105.
  7. Jobs were shipped and customers were billed as follows: Job 101, $8,500; Job 102, $11,330; Job 105, $15,620.

Required:

1. Journalize the entries to record the summarized operations. For a compound transaction, if an amount box does not require an entry, leave it blank.

Entries Description Debit Credit
a. Materials
Accounts Payable
b. Work in Process
Factory Overhead
Materials
Wages Payable
c. Factory Overhead
Accounts Payable
d. Factory Overhead
Accumulated Depreciation-Machinery and Equipment
e. Work in Process
Factory Overhead
f. Finished Goods
Work in Process
g. Sale Accounts Receivable
Sales
g. Cost Cost of Goods Sold
Finished Goods

2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.

Work in Process
(b) (f)
(e)
Bal.

Finished Goods
(f) (g)
Bal.

3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.

Hildreth Company Schedule of Unfinished Jobs
Job Direct Materials Direct Labor Factory Overhead Total
No. 104 $ $ $ $
No. 106
Balance of Work in Process, April 30 $

4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.

Hildreth Company Schedule of Completed Jobs
Job Direct Materials Direct Labor Factory Overhead Total
Finished Goods, April 30 (Job 103) $ $ $ $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Environmental Health And Safety Audits A Compendium Of Thoughts And Trends

Authors: Lawrence B. Cahill

2nd Edition

1598889737, 978-1598889734

More Books

Students also viewed these Accounting questions