Chapter 12 HW CEX.12.01 CEX.12.02 CEX.12.03 CEX.12.04 Hide or show questions Progress:4/4 items eBook Question Content Area Activity-Based Flexible Budgeting Foy Company has a welding

Chapter 12 HW

  1. CEX.12.01
  2. CEX.12.02
  3. CEX.12.03
  4. CEX.12.04

Hide or show questions

Progress:4/4 items

  1. eBook

    Question Content Area

    Activity-Based Flexible Budgeting

    Foy Company has a welding activity and wants to develop a flexible budget formula for the activity. The following resources are used by the activity:

    Four welding units, with a lease cost of $12,000 per year per unit

    Six welding employees each paid a salary of $50,000 per year (A total of 9,000 welding hours are supplied by the six workers.)

    Welding supplies: $300 per job

    Welding hours: Three hours used per job

    During the year, the activity operated at 90 percent of capacity and incurred the following actual activity and resource costs.

    Lease cost: $48,000

    Salaries: $315,000

    Parts and supplies: $805,000

    Required:

    Question Content Area

    1. Prepare a flexible budget formula for the welding activity using welding hours as the driver.

    Welding cost = $fill in the blank 20e72e08ffb306a_1 + $fill in the blank 20e72e08ffb306a_2 X

    Question Content Area

    2. Prepare a performance report for the welding activity. In the last column of Foy Company Activity-Based Performance Report, if variance amount is unfavorable select "U", select "F", if it is Favorable and select "NA" if there is no variance.

    Foy Company Activity-Based Performance Report
    Activity Actual Cost Budgeted Cost (90% level) Budget Variance Variance
    Welding:
    Fixed cost $- Select - $- Select - $- Select -

    FUNA

    Variable cost - Select - - Select - - Select -

    FUNA

    Question Content Area

    3. What if welders were hired through outsourcing and paid $30 per hour (the welding equipment is provided by Foy)? Repeat Requirement 1 for the outsourcing case.

    Welding cost = $fill in the blank 7ff439ff3f9afcc_1 + $fill in the blank 7ff439ff3f9afcc_2 X

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions