Chapter 9 Exercises 1.A certain project has three activities on its critical path. Activity A's normal completion time is five days. It can be crashed

Chapter 9

Exercises

1.A certain project has three activities on its critical path. Activity A's normal completion time is five days. It can be crashed to three days at a cost of $500. Activity B's normal completion time is six days, and it can be crashed to four daysat a costof $50. Activity C's normal completion time is eight days. It can be crashed to three days at a cost of $1,000. Which activity should the project manager crash and by how many days? How much will it cost?

2.Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days,and so onuntil it isin an all-crashmode. Identify how much it would cost for each day you crash the schedule.

Activity Prodecessor Normal Time Normal Cost Crash Time Crash Cost Crash Cost per day
A _ 12 200 9 350
B A 8 300 8 300
C A 9 250 7 450
D B 6 400 5 600
E B, C 5 150 4 225
F C 10 500 9 650
G D, E, F 8 400 6 900

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

1119563097, 9781119563099

Students also viewed these General Management questions

Question

Do I want people to be more like me?

Answered: 1 week ago