Chec Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go karts: Deluxe and Basic. Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $685,000 960,000 165,000 235,000 360,000 135,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based on 125.000 budgeted direct labor hours. 2. In January of this year, the Deluxe model required 2,500 direct labor hours and the basic model required 6,000 direct labor hours Assign overhead costs to each model using the single plantwide overhead rate. Complete this question by entering your answers in the tabs below. uired 1 Required 2 con direct labor hours and the basic model required 6,000 direct labor thead rate. (Round "OH cost answers to 2 decimal rate for the year, assuming that the company assigns overhead based on 125.000 budge ect labor hours. 2. In January of this year, the Deluxe model required 2,500 direct labor hours and the basic model required 6,000 direct labor lo Assign overhead costs to each model using the single plantwide overhead rate. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based on 125,000 budgeted direct labor hours. Roured 1 Required 2) question by entering your answers in the tabs below. Required 1 CENTRE Required 2 In January of this year, the Deluxe model required 2,500 direct labor hours and the basic model required 6,000 net hoe hours. Assign overhead costs to each model using the single plantwide overhead rate. (Round "Oh cott answers to do places.) Total DL Hours Plantwide OH required Deluxe model Basic model