Check my work Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 157,000 $ 656,000 $ 4.70 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct labor cost Machine-hours used $360 $ 220 31 Compute the total manufacturing cost assigned to Job 400, 3. If Job 400 Includes 50 units, what is the unit product cost for this job? 4. If Moody uses a markup percentage of 120% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute the plantwide predetermined overhead rate. (Round your answer to 2 decimal places.) AM Prodetermined overhead rate per MH Required 2 mp4 Variable manufacturing overhead cost per machine-hour $ 4.70 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: bed Direct materials Direct labor cost Machine-hours used $ 360 $ 220 31 ook int ences Compute the total manufacturing cost assigned to Job 400. 3. If Job 400 includes 50 units, what is the unit product cost for this job? 4. If Moody uses a markup percentage of 120% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute the total manufacturing cost assigned to Job 400. (Round your intermediate calculations to 2 decimal places and your final answer to the nearest dollar amount.) Total manufacturing cost (Required 1 Required 3 > Check my work 7 Variable manufacturing overhead cost per machine-hour 4.70 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: 11.11 points Skipped Direct materials Direct labor cont Machine-hours used $ 360 $ 220 31 eBook Print References Compute the total manufacturing cost assigned to Job 400. 3. If Job 400 includes 50 units, what is the unit product cost for this job? 4. If Moody uses a markup percentage of 120% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? Complete this question by entering your answers in the tabs below. Required: Required 2 Required 3 Required 4 17 Job 400 Includes 50 units, what is the unit product cost for this job? (Round your intermediate calculations and final answer to the nearest whole dollar) Unit product cost