Question

1 Approved Answer

Check your worksheet by changing the estimated total amount of the allocation base in the Data area to 50,000 machine-hours, keeping all of the other

Check your worksheet by changing the estimated total amount of the allocation base in the Data area to 50,000 machine-hours, keeping all of the other data the same as in the original example. If your worksheet is operating properly, the predetermined overhead rate should now be $6.00 per machine-hour. If you do not get this answer, find the errors in your worksheet and correct them.

Data

Allocation base

Machine-hours

Estimated manufacturing overhead cost

$300,000

Estimated total amount of the allocation base

75,000

machine-hours

Actual manufacturing overhead cost

$290,000

Actual total amount of the allocation base

68,000

machine-hours

Enter a formula into each of the cells marked with a ? below

Computation of the predetermined overhead rate

Estimated manufacturing overhead cost

?

Estimated total amount of the allocation base

?

machine-hours

Predetermined overhead rate

?

per machine-hour

Computation of underapplied or overapplied manufacturing overhead

Actual manufacturing overhead cost

?

Manufacturing overhead cost applied to Work in Process during the year:

Predetermined overhead rate

?

per machine-hour

Actual total amount of the allocation base

?

machine-hours

Manufacturing overhead applied

?

Underapplied (overapplied) manufacturing overhead

?

Change all of the numbers in the data area of your worksheet so that it looks like this:

Chapter 3: Applying Excel

2

3

Data

4

Allocation base

Machine-hours

5

Estimated manufacturing overhead cost

$135,300

6

Estimated total amount of the allocation base

33,000

machine-hours

7

Actual manufacturing overhead cost

$131,700

8

Actual total amount of the allocation base

37,000

machine-hours

9

If your formulas are correct, you should get the correct answers to the following questions.

What is the predetermined overhead rate? (Round your answer to 2 decimal places.)

Predetermined overhead________per machine hr

By how much is the manufacturing overhead underapplied or overapplied?

______manufact overhead______

Either print or make a copy of your worksheet in your workbook before proceeding. You will need to refer back to this worksheet.

Change the estimated total amount of the allocation base to 41,000 machine-hours, but keep everything the same as in Requirement 2. The data area of your worksheet should now look like this:

A

B

C

D

1

Chapter 3: Applying Excel

2

3

Data

4

Allocation base

Machine-hours

5

Estimated manufacturing overhead cost

$135,300

6

Estimated total amount of the allocation base

41,000

machine-hours

7

Actual manufacturing overhead cost

$131,700

8

Actual total amount of the allocation base

37,000

machine-hours

By how much is the manufacturing overhead underapplied or overapplied?

______manufact overhead_______

Change the estimated total amount of the allocation base back to 33,000 machine-hours, so that the data area of you worksheet looks exactly the same as in Requirement 2. Now change the actual manufacturing overhead cost from $131,700 to $133,000. The data area of your worksheet should now look like this:

Chapter 3: Applying Excel

2

3

Data

4

Allocation base

Machine-hours

5

Estimated manufacturing overhead cost

$135,300

6

Estimated total amount of the allocation base

33,000

machine-hours

7

Actual manufacturing overhead cost

$133,000

8

Actual total amount of the allocation base

37,000

machine-hours

9

By how much is the manufacturing overhead underapplied or overapplied?

______manufact overhead______

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Auditing: Principles And Techniques

Authors: Richard L. Ratliff, W. Wallace, Walter B. Mcfarland, J. Loeboecke

1st Edition

0894131672, 978-0894131677

More Books

Students also viewed these Accounting questions

Question

i need correct answrrs 2 .

Answered: 1 week ago