chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 2 B A 3 C A 5 D B 4 E
chedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E Cmedia:cmpng D
F D
G F
H Emedia:cmpng G
What is the critical path?
multiple choice
ABDEH
ACEFGH
ACEH
ABDFGH
How many weeks will it take to complete the project?
Which activities have slack, and how much?
multiple choice
Ccm weekssc Fcm weekssc Gcm weeks.
Acm weekssc Bcm weeksc Dcm weeks.
Bcm weekssc Dcm weeksc Ecm weeks.