choose correct answer Your project management plan results in a project schedule that is too long; if the project network diagram cannot change but you

choose correct answer

Your project management plan results in a project schedule that is too long; if the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do?

a.

Monte Carlo analysis.

b.

Fast track the project.

c.

Level the resources.

d.

Crash the project.

In the context of a desirable model of communication between a sender and a receiver, all the following statements are correct EXCEPT:

a.

Receiver should send a feedback message to the sender.

b.

Noise should be at a minimum level.

c.

Receiver must reply to the message after decoding the message.

d.

Receiver should acknowledge first and then agree with the message sent by the sender

Your website development project is newly underway. The team appears to be in the "storming" stage, with several members insisting that the process occurs in a certain way and others unwilling to participate after their views were overruled. You recognize that cooperation and collaboration are imperative for the team to achieve the sponsor's goal of a working prototype within the next few weeks. What is the most helpful action for you to take?

a.

Hold a team meeting and facilitate the creation of a team charter that includes ground rules.

b.

Enroll the team in a course on emotional intelligence so that they will learn to be sensitive to each other's feelings.

c.

Hold a networking event so that team members can get to know each other better

d.

Advise the sponsor that there may be a delay in the prototype delivery.

The cost baseline is developed during which process?

a.

Determine budget

b.

Develop schedule

c.

Monitor & control project work

d.

Estimate costs

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essential Quantitative Methods For Business Management And Finance

Authors: Les Oakshott

7th Edition

1352005697, 978-1352005691

More Books

Students also viewed these General Management questions