Choose the answer below that is INCORRECT about independent capital budgeting projects. a. All independent projects with NPV>0 should be accepted if the capital budget
Choose the answer below that is INCORRECT about independent capital budgeting projects.
a. | All independent projects with NPV>0 should be accepted if the capital budget allows. | |
b. | Only the independent project with the highest NPV should be accepted, all others rejected. | |
c. | Independent projects perform different functions | |
d. | The IRR rule may be correctly used to choose from independent projects. |