Christopher crank uses a machine that can produce 100 cranks per hour. The firm operates 8 hours per day five days per week. Due to
Christopher crank uses a machine that can produce 100 cranks per hour. The firm operates 8 hours per day five days per week. Due to regularly scheduled preventive maintenance, the firm expects the machine to be running during approximately 90% of the available time. Based on experience with other products, the firm expects to achieve an efficiency level for the cranks of 90%. What is the expected weekly output of cranks for this company
Step by Step Solution
There are 3 Steps involved in it
Step: 1