Question
Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly are necessary activities; expediting and storing goods are unnecessary.
Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly are necessary activities; expediting and storing goods are unnecessary. The following data pertain to the four activities for the year ending 20x1 (actual price per unit of the activity driver is assumed to be equal to the standard price):
Activity | Activity Driver | SQ | AQ | SP |
Receiving | Receiving orders | 12,000 | 18,000 | $21 |
Assembly | Labor hours | 75,000 | 90,000 | 15 |
Expediting | Orders expedited | 0 | 6,000 | 50 |
Storing | Number of units | 0 | 12,000 | 7 |
Assume that at the beginning of 20x2, Cicleta trained the assembly workers in a new approach that had the objective of increasing the efficiency of the assembly process. Cicleta also began moving toward a JIT purchasing and manufacturing system. When JIT is fully implemented, the demand for expediting is expected to be virtually eliminated. It is expected to take two to three years for full implementation. Assume that receiving cost is a step-fixed cost with steps of 1,500 orders. The other three activities employ resources that are acquired as used and needed. At the end of 20x2, the following results were reported for the four activities:
Activity | Activity Driver | SQ | AQ | SP |
Receiving | Receiving orders | 12,000 | 12,000 | $21 |
Assembly | Labor hours | 75,000 | 78,000 | 15 |
Expediting | Orders expedited | 0 | 3,000 | 50 |
Storing | Number of units | 0 | 6,000 | 7 |
Required:
Prepare a trend report that shows the non-value-added costs for each activity for 20x1 and 20x2 and the change in costs for the two periods. Enter all your answers as positive amounts. If an amount is zero, enter "0".
Activity | 20x1 | 20x2 | Change |
Receiving | $fill in the blank 1 | $fill in the blank 2 | $fill in the blank 3 |
Assembly | fill in the blank 4 | fill in the blank 5 | fill in the blank 6 |
Expediting | fill in the blank 7 | fill in the blank 8 | fill in the blank 9 |
Storing | fill in the blank 10 | fill in the blank 11 | fill in the blank 12 |
Total | $fill in the blank 13 | $fill in the blank 14 | $fill in the blank 15 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started