Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Cinderella continues to keep an eye on her latest Pumpkin Carriage Project She

Cinderella continues to keep an eye on her latest Pumpkin Carriage Project She knew the project would take 25 ï»¿weeks but dudes see tea il was doing after 20 ï»¿Determine the status of the project (calculate PV, ï»¿EV, ï»¿AC, ï»¿CPI, ï»¿SPI, ï»¿Costto Compiction and Time to Completiren) ï»¿through 20 ï»¿weeks and comment on this 25 ï»¿week project. ï»¿(10 ï»¿marks). ï»¿All amounts are in thousands of dollars, ï»¿is Cindereia as gond Prickin Carriage project manager or should she just stick to manufacturing shoes?
FV. ï»¿EV, ï»¿AC, ï»¿CPI, ï»¿SPI, ï»¿Cost to Completion and Time to Completion = 7 ï»¿marks
Comment on Cinderella's Pumpkin Carriage Project = 3 ï»¿marksDuration (weeks) 
 5 10 15 20 25 
Design new pumpkin carriage 10 6 
prototype new pumpkin 12 6 4 
build new carriage 6 4 5 
prepare pupkin advertising 4 2 
finalize new pumpkin carriage 6 8 
start new pumpkin carriage 12 
total
cumulative
actual 11 16 32 26 0 
cumulative actual

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Purchasing and Supply Chain Management

Authors: W.C Benton

3rd edition

78024110, 978-0078117091, 78117097, 978-0078024115

More Books

Students also viewed these General Management questions

Question

How does foreign investment help the U.S. government?

Answered: 1 week ago