Use the information shown in the following table (assume days for each a time unit): Activity Time A B D E Activity Earliest Earliest

 

Use the information shown in the following table (assume days for each a time unit): Activity Time A B D E Activity Earliest Earliest Start F G 2 1 3 7 3 ??? 4 0 2 2 3 5 5 11 Latest Finish Latest Start Finish ??? 3 5 10 8 11 15 0 3 2 4 ??? 5 11 2 4 5 11 11 11 15 Slack 0 1 0 ??? 3 0 0 QUESTIONS: A) What is the slack time for Activity D? B) What is the earliest finish time for Activity A? C) What is the latest start time for Activity E? D) What is the activity time for Activity F? E) identify the critical path? F) What is the project duration?

Step by Step Solution

3.39 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

A What is the slack time for Activity D Answer The slack time for Activity D is 1 day B What is the ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Law The Ethical Global and E-Commerce Environment

Authors: Jane Mallor, James Barnes, Thomas Bowers, Arlen Langvardt

15th edition

978-0073524986, 73524980, 978-0071317658

More Books

Students also viewed these General Management questions

Question

What are some of the benefits of being a critical thinker? (p. 231)

Answered: 1 week ago