Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments

Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 1020 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture of the down payment. Occasionally, homes remain unsold for as long as three months after construction. In these situations, sales price reductions are used to promote the sale.

During 2016, Citation began construction of an office building for Altamont Corporation. The total contract price is $17 million. Costs incurred, estimated costs to complete at year-end, billings, and cash collections for the life of the contract are as follows:

2016 2017 2018
Cost incurred during the year $ 3,400,000 $ 8,075,000 $ 3,825,000
Estimated costs to complete as of year-end 10,200,000 3,825,000
Billings during the year 1,700,000 8,500,000 6,800,000
Cash collections during the year 1,530,000 7,070,000 8,400,000

Also during 2016, Citation began a development consisting of 12 identical homes. Citation estimated that each home will sell for $760,000, but individual sales prices are negotiated with buyers. Deposits were received for eight of the homes, three of which were completed during 2016 and paid for in full for $760,000 each by the buyers. The completed homes cost $570,000 each to construct. The construction costs incurred during 2016 for the nine uncompleted homes totaled $3,420,000.

Required:
1.

Which method is most equivalent to recognizing revenue at the point of delivery?

Completed contract
Percentage-of-completion

2.

Answer the following questions assuming that Citation uses the completed contract method for its office building contracts:

a.

How much revenue related to this contract will Citation report in its 2016 and 2017 income statements?

b.

What is the amount of gross profit or loss to be recognized for the Altamont contract during 2016 and 2017? (Loss amounts should be indicated with a minus sign.)

c.

What will Citation report in its December 31, 2016, balance sheet related to this contract? (Ignore cash.)

3.

Answer the following questions assuming that Citation uses the percentage-of-completion method for its office building contracts.

a.

How much revenue related to this contract will Citation report in its 2016 and 2017 income statements?

b.

What is the amount of gross profit or loss to be recognized for the Altamont contract during 2016 and 2017? (Loss amounts should be indicated with a minus sign.)

c.

What will Citation report in its December 31, 2016, balance sheet related to this contract? (Ignore cash.)

4.

Assume the same information for 2016 and 2017, but that as of year-end 2017 the estimated cost to complete the office building is $7,650,000. Citation uses the percentage-of-completion method for its office building contracts.

a.

How much revenue related to this contract will Citation report in the 2017 income statement?

b.

What is the amount of gross profit or loss to be recognized for the Altamont contract during 2017? (Loss amounts should be indicated with a minus sign.)

c.

What will Citation report in its 2017 balance sheet related to this contract? (Ignore cash.)

5. Which method of accounting should Citation Builders, Inc adopt for its single-family houses?
Completed contract method
Percentage-of-completion method

6.

What will Citation report in its 2016 income statement and 2016 balance sheet related to the single-family home business (ignore cash in the balance sheet)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Environmental Health And Safety Audits

Authors: Lawrence B. Cahill, Raymond W. Kane

9th Edition

1605907081, 9781605907086

More Books

Students also viewed these Accounting questions

Question

S 3 Glacier is designed for 9 9 . 9 9 % availability. True False

Answered: 1 week ago