Question

1 Approved Answer

Civil Engineering Which of the following are the right practice of negotiating cost claims? I) When assessment is completed the consultant contract administrator (work for

Civil Engineering

Which of the following are the right practice of negotiating cost claims?

I) When assessment is completed the consultant contract administrator (work for the superintendent/principal) should contact the contractor in due course for discussion.

II) If the contractor accepts the valuation, the claim amount should be paid in the next monthly payment.

III) If the contractor does not accept the valuation, set the amount pending until the final account.

IV) Try to come up with an agreement through negotiation. Try to prevent the disagreement from developing to a dispute that needs to be resolved through arbitration or litigation.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Routledge To Global Political Economy Conversations And Inquiries

Authors: Ernesto Vivares

1st Edition

1351064525, 9781351064521

More Books

Students also viewed these Economics questions