Civil Engineers team has one foremen costs SR76.72/hr, one cement finisher costs SR1.32/min, five laborers cost SR68.37/hr, and one equipment operator costs SR128.77/hr. This team
Civil Engineers team has one foremen costs SR76.72/hr, one cement finisher costs SR1.32/min, five laborers cost SR68.37/hr, and one equipment operator costs SR128.77/hr. This team can install 173 Cubic yards of concrete per 17 hour a day. Find the daily cost for the team per cubic yard of concrete.