Clark Construction is building a set of new condos in the Virginia Beach. The project consists of 18 buildings, each housing 12 condominiums. Each building

Clark Construction is building a set of new condos in the Virginia Beach. The project consists of 18 buildings, each housing 12 condominiums. Each building will border the Virginia Beach Golf Course designed by J. M. Architects. The minimum price for a condominium unit is $300,000, and buyers expect a high-quality project. Response to the initial promotion was so great that CLARK Construction pre-sold all 216 units based solely on an architect's conception and schematic plans of the project. One reason for the quick sell-out may have been the -YOU CAN MOVE IN BY OCTOBER- campaign. As part of this campaign, CLARK promised rebates of $20,000 cash to all 216 buyers if all the facilities, buildings, and other amenities were not completed by October 15.

The following PERT/CPM network (image attached) details the precedence for the activities of the tasks remaining to be completed in the project. R and T will be subcontracted. Three-time estimates (in days) for each of the other activities needed for each condo have been determined and are given in the following table (Note: all the condos will be constructed concurrently) Use a full day as the smallest unit for scheduling the activities:

image text in transcribed
ACTIVITY CODE AND DESCRIPTION Estimated Activity Duration (a, m, b) Dependencies optimistic most likely pessimistic Al. Land measurements 5 8 11 B2. Layout of measurement stakes 7 12 17 A C3. Analysis of surrounding environment 10 17 24 D4. Building of foundation 12 22 32 B E5. Approval of construction papers 6 13 20 C F6. Layout of building framework 11 15 19 C G7. Gas line instalment 9 18 27 C H8. Electrical wiring 25 27 29 B, G 19. Interior plumbing 18 20 22 E, B J10. Wall construction 12 25 38 D, H K11. Insulation 10 23 36 I, F L12. Drywall 15 20 25 F, I M13. Roofing 3 10 17 K, J N14. Restaurant construction 25 40 55 G 015. Swimming pool 9 20 31 J, K, L, G P16. Fencing 6 10 14 J, K, L, G Q17. Telephone lines 12 22 32 M, O R18. Completion of underground M, O $19. Snack bar 10 20 30 N T20. Stream building N U.21 Outside lighting 8 12 16 P, S V22. Parking lots 3 5 7 P, S, Q, W23. Drainage construction 5 10 15 P, S, Q, T X24. Safety inspection 9 15 21 U, W Y25. Landscaping 6 24 42 R, V Z26. Final permits/releases 10 15 20 X, Y

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Marketing

Authors: Nigel Piercy and David Cravens

10th edition

78028906, 978-0078028908

More Books

Students also viewed these General Management questions

Question

Solve for the indicated letter. 1-3 b t 2b - 1 =fo for t 2

Answered: 1 week ago

Question

Historical events in chronological order?

Answered: 1 week ago

Question

Reforms movement amoung the muslims called the........ movement ?

Answered: 1 week ago

Question

India has a federal system of government with a strong........?

Answered: 1 week ago

Question

Famous theory poverty and un british rule in India?

Answered: 1 week ago