Clarke Corporation manufactures three products (X-1.X-2, and X-3) utilizing, in one of the processes, a single machine for all products. Data on the individual products follow. Price per unit Variable cost per unit Machine hours per unit Maximun units demand per period X-1 $ 176 $ 88 1.0 395,000 X-2 $ 276 $ 144 2.5 188,000 X-3 $ 552 $ 316 4.0 77,000 The single machine used for all three products has a maximum capacity of 878,000 hours per period. Required: a. How many units of each product should be produced each period? b. A local engineering firm has suggested to Clarke that it might be able to increase the capacity on the machine. What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? c. Suppose the maximum capacity on the machine was 471,000 hours (instead of 878,000 hours). What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? d. At what capacity (in machine hours) would the machine no longer be a bottleneck? Required: a. How many units of each product should be produced each period? b. A local engineering firm has suggested to Clarke that it might be able to increase the capacity on the machine. What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? c. Suppose the maximum capacity on the machine was 471,000 hours (instead of 878,000 hours). What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? d. At what capacity (in machine hours) would the machine no longer be a bottleneck? Complete this question by entering your answers in the tabs below. Required A Required B Required cRequired D How many units of each product should be produced each period? IX.1 X2 X-3 units units units Required: a. How many units of each product should be produced each period? b. A local engineering firm has suggested to Clarke that it might be able to increase the capacity on the machine. What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? c. Suppose the maximum capacity on the machine was 471,000 hours (instead of 878,000 hours). What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? d. At what capacity (in machine hours) would the machine no longer be a bottleneck? Complete this question by entering your answers in the tabs below. Required A Required B Required Required D A local engineering firm has suggested to Clarke that it might be able to increase the capacity on the machine. What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? Maximum amount payable Required: a. How many units of each product should be produced each period? b. A local engineering firm has suggested to Clarke that it might be able to increase the capacity on the machine. What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? c. Suppose the maximum capacity on the machine was 471,000 hours (instead of 878,000 hours). What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? d. At what capacity (in machine hours) would the machine no longer be a bottleneck? Complete this question by entering your answers in the tabs below. Required A Required B Required Required D Suppose the maximum capacity on the machine was 471,000 hours (instead of 878,000 hours). What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? Maximum amount payable Required: a. How many units of each product should be produced each period? b. A local engineering firm has suggested to Clarke that it might be able to increase the capacity on the machine. What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? c. Suppose the maximum capacity on the machine was 471,000 hours (instead of 878,000 hours). What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? d. At what capacity (in machine hours) would the machine no longer be a bottleneck? Complete this question by entering your answers in the tabs below. Required A Required B Required Required D At what capacity (in machine hours) would the machine no longer be a bottleneck? Capacity machine hours