Question
Clever Engineering is a company that carries out various contracts throughout the UK. The company has had its offer of 288,000 for a contract in
Clever Engineering is a company that carries out various contracts throughout the UK.
The company has had its offer of 288,000 for a contract in the North-East accepted and work is due to begin in March.However the company has also been asked to undertake a contract on the South Coast-the price offered for this contract is 352,000.The contracts cannot be taken simultaneously due to constraints on staff site management and on plant and machinery available.An 'escape clause' enables the company to withdraw from the North-East contract (if it decides to undertake the South Coast contract instead) but Clever Engineering will have to pay a penalty of 28,000.
The following information is available for each contract:
North-East
South Coast
Materials:
Material X (in stock at original cost)
21,600
Material X (firm order placed at original cost)
30,400
Material X (not yet ordered, current cost)
60,000
Material Y (in stock at original cost)
24,800
Material Z (not yet ordered, current cost)
71,200
Labour - hired locally
86,000
110,000
Site management
34,000
34,000
Staff accommodation and travel for site management
6,800
5,600
Plant on site - depreciation
9,600
12,800
Total Local Contract Costs
248,400
258,400
Head Office Costs (allocated at a rate of 5% of local contract costs)
12,240
12,920
260,640
271,320
Contract Price
288,000
352,000
Estimated Profit on Contract
27,360
80,680
Notes:
1.X,Y and Z are three building materials.Material X is not in common use and has minimal resale value.However it could be used on other contracts as a substitute for another material that currently costs 10% less than the original cost of Material X.The price of Material Y,which is in common use, has doubled since it was purchased originally.This material could be sold for 42,160 or alternatively could be kept for use on other contracts in the following year.
Materials:
Material X:
Relevant Cost:
Relevant Cost:
Material Y:
Relevant Cost:
Relevant Cost:
2.The company is confident that manual labour,both skilled and unskilled,could be hired locally on a sub-contracting basis(that is,they would not be permanent workers)to meet the needs of each of the contracts.
3.The plant which would be needed for the South Coast contract has been owned by Clever Engineering for some years and annual depreciation is 12,800 on a straight-line basis.If the North-East contract is undertaken,less plant will be required but the surplus plant would be hired out for the period of the contract at a rental of 6,000.
4.Salaries and general costs of operating Head Office amount to 108,000 each year.There are usually ten contracts being supervised at the same time.
5.Site management is treated as a fixed cost.
Required:
In the LECTURE:
Calculate the relevant costs of the North-East contract,explaining how you arrived at each relevant cost.Present the relevant costs in a Relevant Cost Statement.
For the SEMINAR:
i.Calculate the relevant costs of the North-East contract,explaining how you arrived at each relevant cost.Present the relevant costs in a Relevant Cost Statement.
ii.Determine which of the two contracts would be more beneficial for Clever Engineering,giving reasons for your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started