CMIT level 2 during the construction phase, one example of a quality control task is? the CM comparing the contractors work to the contract documents
CMIT level 2
during the construction phase, one example of a quality control task is?
- the CM comparing the contractors work to the contract documents
- the CM reporting safety violations to the owner
- the contractor submitting change order requests to avoid delays
- the contractor verifying the work meetings specification requirements