Question
1 Approved Answer
(CO6) In a PERT chart, the path with the greatest total duration time that represents the longest amount of time required to complete the total
(CO6) In a PERT chart, the path with the greatest total duration time that represents the longest amount of time required to complete the total project is referred to as _____. Group of answer choices critical path benchmarking check path due process
Step by Step Solution
There are 3 Steps involved in it
Step: 1