Cobe Company has manufactured 295 partially finished cabinets at a cost of $73,750. These can be sold as is for $88,500. Instead, the cabinets can
Cobe Company has manufactured 295 partially finished cabinets at a cost of $73,750. These can be sold as is for $88,500. Instead, the cabinets can be stained and fitted with hardware to make finished cabinets. Further processing costs would be $17,700, and the finished cabinets could be sold for $118,000. (a) Prepare a sell as is or process further analysis of income effects. (b) Should the cabinets be sold as is or processed further and then sold