Coefficients shown by a regression program are: Intercept 7,600X Variable 15.10 The cost driver used is machine hours. Required: A. Using the results of regression,
Coefficients shown by a regression program are:
Intercept 7,600X
Variable 15.10
The cost driver used is machine hours.
Required:
A.Using the results of regression, calculate the fixed cost of maintenance and the variable rate per machine hour.
Fixed cost$
Variable rate$ per machine hour
B.Using the results of regression, construct the cost formula for the total maintenance cost.
Total maintenance cost=Fixed cost+Variable cost=$+($per machine hour Number of machine hours)
C.Calculate the budgeted cost for maintenance assuming that 610 hours are worked next month.
$
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started