Question
1 Approved Answer
Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers
Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: Activity A B C D E F G a 4 1 7 6 3 1 3 Time (days) m 5 2 7 10 10 5 7 b 9 5 12 19 6 10 Immediate Predecessor(s) A A B, C D D Activity H I J K L M N a 3 2 2 7 1 1 6 Time (days) m 3 5 4 9 6 3 9 b 7 8 7 13 8 4 10 Immediate Predecessor(s) E, F G, H 1 1 J K L, M a) The expected completion time of the project = 52.33 days (round your response to two decimal places). The activities that represent the project's critical path are A-C-E-H-1-K-M-N b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 54 days or less = 7 (round your response to two decimal places). c) Using the standard normal table, the number of days that would result in 99% probability of completion = days (round your response to two decimal places). Coleman Rich Control Devices, Inc, peoduces cuslom-bue twlay devices for auto makers. The most recent projoct undertaken by Rich requires 14 different activities. Rich's manejen would like to determine the total project completion fime (in doys) and those activities then fle along the critical path The eppropriate dats are shown in the following table: a) The expected completion time of the proinct = days (found your response to mo decimal places). The activites that represent the propects critical path am docimal placens). e) Using the standard normal table, the number of days that would result in grsw probabilty of completion * days (round yoir respense to mo decimal plecea)
Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: Activity A B C D E F G a 4 1 7 6 3 1 3 Time (days) m 5 2 7 10 10 5 7 b 9 5 12 19 6 10 Immediate Predecessor(s) A A B, C D D Activity H I J K L M N a 3 2 2 7 1 1 6 Time (days) m 3 5 4 9 6 3 9 b 7 8 7 13 8 4 10 Immediate Predecessor(s) E, F G, H 1 1 J K L, M a) The expected completion time of the project = 52.33 days (round your response to two decimal places). The activities that represent the project's critical path are A-C-E-H-1-K-M-N b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 54 days or less = 7 (round your response to two decimal places). c) Using the standard normal table, the number of days that would result in 99% probability of completion = days (round your response to two decimal places).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started