Collingwood Contractors ( CC ) designs and builds new model homes for individual customers. CC has developed a reputation in the market for relatively upscale,

Collingwood Contractors (CC) designs and builds new model homes for individual customers. CC has developed a reputation in the market for relatively upscale, unique designs with high-end finishings. CC has developed several formulas, which it uses to estimate costs and provide price quotes for prospective buyers. These include costs for materials, labor, and other resources. Although multiple configurations are possible for any house, CC uses three levels (or tiers) to represent increasing levels of luxury in terms of materials used. In addition, the customer can choose among three levels of increasingly sophisticated appliances and other house equipment. Finally, there is cost to bring utilities (electricity, water, and so on) to the house if required. Of course, these estimates are dependent on the region of the country and whether the lot is located in a city or in a suburb or rural area. If the building site is in a city, a premium is added based on the building and equipment costs. The following are the cost estimates for one region in the Northwest:
Design and administrative costs $ 45,000
Building costs per square foot (Tier I)120
Building costs per square foot (Tier II)190
Building costs per square foot (Tier III)245
Equipment (appliances, and so on)-- Ruby 23,000
Equipment (appliances, and so on)-- Sapphire 32,000
Equipment (appliances, and so on)-- Emerald 41,000
Utilities required? If yes, ...44,000
City premium (applied to building and equipment costs)15%
Required:
A customer has expressed interest in having CC build a Tier III, 5,500-square-foot home. The building site is a city lot and the customer wants the Sapphire level equipment. Based on the engineering estimates above, what will such a house cost to build? No additional utilities access is required.
Another customer has expressed interest in having CC build a smaller, Tier I, home, but with emerald-level equipment. This home will be on a vacant lot in the country and require utilities access to be added. The customer has chosen a 3,200-square-foot design. Based on the engineering estimates above, what will such a house cost to build?a. A customer has expressed interest in having CC build a Tier III, 5,500-square-foot home. The building sit
customer wants the Sapphire level equipment. Based on the engineering estimates above, what will such
additional utilities access is required.
b. Another customer has expressed interest in having CC build a smaller, Tier I, home, but with emerald-lev
will be on a vacant lot in the country and require utilities access to be added. The customer has chosen a
Based on the engineering estimates above, what will such a house cost to build?
Complete this question by entering your answers in the tabs below.
A customer has expressed interest in having CC build a Tier III, 5,500-square-foot home. The building site is a ci
customer wants the Sapphire level equipment. Based on the engineering estimates above, what will such a house
build? No additional utilities access is required.
Required B
Design costs
Building Costs
City Premium
Utilities (if required)
Estimated Cost
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Impact On Decision Makers

Authors: Gary A. Porter, Curtis L. Norton

7th Edition

1111464936, 978-1111464936

More Books

Students also viewed these Accounting questions

Question

7 Describe the role of an HR business partner

Answered: 1 week ago

Question

5 Explain the concept of the psychological contract.

Answered: 1 week ago