Question
Colnago manufactures sports bikes. Each bike is assembled using the following components 1 frame 2 wheels 1 handlebar A frame is made up of 1
Colnago manufactures sports bikes. Each bike is assembled using the following components
1 frame
2 wheels
1 handlebar
A frame is made up of 1 seat
Each wheel requires 4 screws
Each handlebar requires 3 screws
Both the wheel and handlebar require the same type of screw
Assume constant production. The demand for bicycles in January is expected to be 560 units (140 for each of the 4 weeks in January)
Lead-time for each component is as follows,
bike- 3 weeks
frame- 2 weeks
wheel 1 weeks
seat- 2 weeks
handlebar- 1 week
screw- 2 weeks
The order strategies for each item are given below,
bike- EOQ of 150
frame- EOQ of 200
wheel LFL
seat- LFL
handlebar- EOQ of 250
screw- EOQ of 450
The following quantities of each item are on hand,
bike- 85
frame- 20
wheel 10
seat- 0
handlebar- 25
screw- 0
Draw the bill-of-materials (product structure tree). Develop a 14-week Materials Requirement Planning schedule to ensure required production in January.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started