Question
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.
Activity | Description | Immediate Predecessor | Time (weeks) |
---|---|---|---|
A | Survey building site | 5 | |
B | Develop initial design | 8 | |
C | Obtain board approval | A, B | 13 |
D | Select architect | C | 2 |
E | Establish budget | C | 5 |
F | Finalize design | D, E | 15 |
G | Obtain financing | E | 11 |
H | Hire contractor | F, G | 6 |
(a)
Draw a project network. (Submit a file with a maximum size of 1 MB.)
This answer has not been graded yet.
(b)
Identify the critical path. (Enter your answers as a comma-separated list.)
(c)
Develop the activity schedule for the project.
Activity | Earliest Start | Latest Start | Earliest Finish | Latest Finish | Slack |
---|---|---|---|---|---|
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G | |||||
H |
(d)
Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?
The expected completion time is weeks, which is ---Select--- less greater than 1 year.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started