Comet Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat is as follows: Materials (0.85
Comet Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat is as follows:
Materials (0.85 yards x $12.00) = $10.20
Direct Labor (1.3 hours x $14.00) = $18.20
In March, the company produced 4,000 band hats; 3,600 yards of material were purchased and used for $44,100; and 3,400 direct labor hours were worked at a cost of $45,050.
Required:
a. Calculate the direct materials quantity variance
b. Calculate the direct materials price variance
c. Calculate the direct labor hour variance
d. Calculate the direct labor rate variance
Indicate whether the variance are favorable (FAV) or unfavorable (UNF).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started