Company B projects the following cash flows from a project: Year Cash Flow 0 -$16,400 1 7,100 2 8,400 3 6,900 What is the NPV
Company B projects the following cash flows from a project:
Year Cash Flow 0 -$16,400 1 7,100 2 8,400 3 6,900
What is the NPV of the project at 0%, 10%, 20%, and 30% discount rates? What is the IRR of the project?