Company: EFG Energy Scenario: Cost Control in Projects Data: Projected Costs: $2,000,000 Actual Costs: $2,200,000 Projected Timeline: 12 months Actual Timeline: 14 months Requirements: Calculate
- Company: EFG Energy
Scenario: Cost Control in Projects
Data:
- Projected Costs: $2,000,000
- Actual Costs: $2,200,000
- Projected Timeline: 12 months
- Actual Timeline: 14 months
Requirements:
- Calculate the cost variance.
- Determine the timeline variance.
- Discuss the reasons for cost and timeline variances.
- Provide strategies for better cost control in future projects.