Company PLAW is building 10 firewall servers each has a value of CAD$1000 expected to be completed in 10 weeks in proportion. At the end
Company PLAW is building 10 firewall servers each has a value of CAD$1000 expected to be completed in 10 weeks in proportion. At the end of week 4, only 3 servers are completed? 1. what is the budget at completion? 2. By end of week 4, calculate Schedule Variance, Schedule Performance Index, Cost Variance, Cost Performance Index, step by step computation is needed?