Company receives an order for the printing of brochures. They are produced in a two-step process. Step one will take two days. Step two will
Company receives an order for the printing of brochures. They are produced in a two-step process. Step one will take two days. Step two will take one day. The customer wants them in five days. The scheduler projects a completion date of nine days.
The scheduler has most likely used __________.
Backward scheduling and infinite loading
Backward scheduling and finite loading
Forward scheduling and infinite loading
Forward scheduling and finite loading