Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity - based costing ( ABC ) . The controller identified two activities and
Comparing ABC and Plantwide Overhead Cost Assignments
Wellington Chocolate Company uses activitybased costing ABC The controller identified two activities and their budgeted costs:
Setting up equipment $
Other overheard $
Setting up equipment is based on setup hours, and other overhead is based on oven hours.
Wellington produces two products, Fudge and Cookies. Information on each product is as follows:
Fudge Cookies
Units produced
Setup hours
Oven hours
Calculate the activity rate for a setting up equipment and b other overhead.
a Setting up equipment $fill in the blank per setup hour
b Other overhead $fill in the blank per oven hour
How much total overhead is assigned to Fudge using ABC?
$fill in the blank
What is the unit overhead assigned to Fudge using ABC? Round to the nearest cent.
$fill in the blank per unit
Now, ignoring the ABC results, calculate the plantwide overhead rate, based on oven hours. Round to the nearest cent.
$fill in the blank per oven hour
How much total overhead is assigned to Fudge using the plantwide overhead rate?
$fill in the blank
a The difference in the total overhead assigned to Fudge is different under the ABC system and nonABC system because
b What is the difference in total overhead assigned to fudge under the two methods?
$fill in the blank
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started