Question
1 Approved Answer
Comparing actual cost variance across projects uses an index rather than dollar amount, because ________. Monetary variance does not include foreign currency Dollar variance is
Comparing actual cost variance across projects uses an index rather than dollar amount, because ________. Monetary variance does not include foreign currency Dollar variance is relative to the size of the project Variances in schedule are not included Current interest rates are not included in monetary value