Comparing Two Products under Traditional and Activity-Based Costing Compare two projects under development by the same company. The following are a few aspects of each
Comparing Two Products under Traditional and Activity-Based Costing
Compare two projects under development by the same company. The following are a few aspects of each product's development process relevant to costs.
Product S Requires 3,840 hours of testing
Requires 5,250 units of computing power
Requires 20 developer hours to implement
Product T Requires 960 hours of testing
Requires 2,250 units of computing power
Requires 80 developer hours to implement
Cost Items Cost of Each Activity Testing:$30,000 Computing power:$45,000 Developer hourly cost:$11 per hour
Traditional Costing
Traditional costing would take the proportion of a direct cost, such as direct labor hours, and use it as the basis for allocating overhead costs, such as computing power and testing. In the following table, use developer hours as the basis for assigning overhead costs (computing and developer costs) to each project. If required, round your answers to the nearest dollar.
Product S
Percentage of developer hours 20%
Testing cost$________
Computing cost$____
Developer cost$____
Total cost$___
Product T
Percentage of developer hours 80%
Testing cost$________
Computing cost$____
Developer cost$____
Total cost$___
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started