Question
Comparing Two Products under Traditional and Activity-Based Costing Compare two projects under development by the same company. The following are a few aspects of each
Comparing Two Products under Traditional and Activity-Based Costing
Compare two projects under development by the same company. The following are a few aspects of each products development process relevant to costs.
Product A | Product B | |
Requires 3,520 hours of testing | Requires 880 hours of testing | |
Requires 4,900 units of computing power | Requires 2,100 units of computing power | |
Requires 20 developer hours to implement | Requires 80 developer hours to implement | |
|
Traditional Costing
Traditional costing would take the proportion of a direct cost, such as direct labor hours, and use it as the basis for allocating overhead costs, such as computing power and testing. In the following table, use developer hours as the basis for assigning overhead costs (computing and developer costs) to each project If required, round your answers to the nearest dollar.
Product A | Product B | |||
Percentage of developer hours | 20% | Percentage of developer hours | 80% | |
Testing cost | $ 5,104 | Testing cost | $ 20,416 | |
Computing cost | $ 7,700 | Computing cost | $ 30,800 | |
Developer cost | $ 220 | Developer cost | $ 880 | |
Total cost | $ 13,024 | Total cost | $ 52,096 |
Activity-Based Costing
Using the data above for products A and B, calculate the costs using activity-based costing. Allocate the costs of testing, computing, and development based on the rates of activity consumed by each product's development process. If required, in your computations, round per unit costs to the nearest cent. Round your final answers to the nearest dollar.
Cost | Activity Base |
Testing | Hours of testing |
Computing cost | Units of computing power |
Developer cost | Development hours |
Product A | Product B | |||
Testing cost | $ 20,416 | Testing cost | $ 5,104 | |
Computing cost | $ 26,950 | Computing cost | $ 11,550 | |
Developer cost | $ 220 | Developer cost | $ 880 | |
Total cost | $ 47,586 | Total cost | $ 17,534 |
(1) Activity-based costing for varying batch production
A manufacturing company has the following two activities associated with completion of products:
The setting up of machines for running batches of products
The actual production of units produced
The company has annual manufacturing overhead costs of $2,000,000, of which $200,000 is directly involved in setting up machines for batch runs. During the year, the company expects to perform 400 machine setups, one setup per batch for a total of 400 batches of production. Assume that the batch sizes vary considerably, but the work involved in setting up the machines is not appreciably different from one job to the next.
If the company estimates that the $200,000 costs associated with setups will yield 400 setups this year, the cost associated directly with each setup will be ($______) per setup. Because each job will require its own setup, setup costs are viewed as batch costs. Because $200,000 of the $2,000,000 are costs associated with setups, this means that costs associated directly with the production of units equal ($______)
(2)
APPLY THE CONCEPTS: Calculate the batch-level cost
Determine what batch-level costs will be, both with activity-based costing (ABC) and without, to understand the method and compare and contrast both approaches. Assume that overhead not associated with setup costs is caused by production activities associated with the companys 100,000 machine hours. If an amount is zero, enter "0". Round unit costs to the nearest cent.
With ABC | Without ABC | |||
Total setup costs | $ | $0 | ||
Number of setups | 400 | Not applicable | ||
Overhead costs per setup | $ | $ | ||
Total manufacturing overhead costs | $2,000,000 | $2,000,000 | ||
Less: Cost traced to machine setups | $ | $ | ||
Overhead costs allocated on machine hours | $ | $2,000,000 | ||
Machine hours | 100,000 | 100,000 | ||
Overhead costs per machine hour | $ | $ | ||
Formula for allocating manufacturing O/H costs | $ | setup cost per batch + $ per machine hour | $ | per machine hour |
The effect of batch-level costs spread among varying levels of production |
APPLY THE CONCEPTS: Assign the costs at the unit level (small batch)
Now that you've determined what the cost calculation is at the batch level, extrapolate this down to the unit level to see precisely how much each unit is costing for any given-sized batch of production. For this purpose, assume that the company is considering taking on a contract for 5,000 units and it currently produces 50 units per machine hour. Assign costs with and without activity-based costing. If an amount is zero, enter "0". Round unit costs to the nearest cent.
With ABC | Without ABC | |
Overhead for setting up machine | $ | $ |
Number of units in batch | Not applicable | |
Manufacturing overhead caused by batch setup per unit | $0.10 | Not applicable |
Manufacturing overhead costs per machine hour | $ | $ |
Number of units produced per machine hour | ||
Manufacturing overhead caused by production per unit | $ | $ |
Total manufacturing overhead allocated per unit | $ | $ |
APPLY THE CONCEPTS: Assign costs at the unit level (large batch)
If the company manufactures 50,000 units and produces 50 units per machine hour, how would the costs look at this batch level?
With ABC | Without ABC | |
Overhead for setting up machine | $ | $ |
Number of units in batch | Not applicable | |
Manufacturing overhead caused by batch setup per unit | $0.01 | Not applicable |
Manufacturing overhead costs per machine hour | $ | $ |
Number of units produced per machine hour | ||
Manufacturing overhead caused by production per unit | $ | $ |
Total manufacturing overhead allocated per unit | $ | $ |
(What is the reason for the lower per-unit cost when the batch contains more units?)
Select
A. The batch-level costs decrease with a larger batch size due to increased effectiveness in the production process.
B. The batch-level costs decrease with a smaller batch size due to increased efficiency in the production process.
C. There is no difference in the per-unit cost for different batch sizes under activity-based costing.
D. When the batch-level costs are spread across a greater number of units, the cost per unit decreases.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started