Complete the risk reserve analysis using the risk register provided. Fill in the ALL the blank fields, including totals. Calculate the EMV Reserve Amounts for
Complete the risk reserve analysis using the risk register provided. Fill in the ALL the blank fields, including totals. Calculate the EMV Reserve Amounts for each risk to show you know how to do the calculations. Show actual costs based on the risk status, including $0 when appropriate.
Risk IDCost ImpactProbabilityEMV Reserve AmountStatusActual Costs so far1($2,000)15%$Avoided and closed$2($1,500)55%$Open no change$3$1,00090%$Open no change$4($7,200)60%$Closed, actual cost $5,000$5($5,200)30%$Open Probability increased to 50%$TOTALS$ $0$
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started