Question

1 Approved Answer

Complete this exercise in MSProject. Submit both your MSProject file and your answers to the questions below. You can use your solution to the scheduling

Complete this exercise in MSProject. Submit both your MSProject file and your answers to the questions below. You can use your solution to the scheduling exercise (before any tasks were crashed) as the basis for this exercise.

Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:

Task

Predecessor

Duration

Resource

A

-

2

HR Manager

B

-

7

HR Analyst

C

A

4

HR Analyst

D

B, C

8

HR Analyst

E

D

8

Benefits Coordinator

F

D

6

Benefits Coordinator

G

E

3

HR Analyst

H

E, F

6

HR Manager

  1. Before adding resources, the project takes 29 days. Once resources constraints are entered and leveled, what is the total number of days to complete the project?
  2. According to the project statistics, what is the planned cost of the project?
  3. If the HR Manager is only available to work on the project 50% of the time, rather than dedicated to the project full-time, how many days will it take to complete the project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Intelligence

Authors: Efraim Turban, Ramesh Sharda, ...more

2nd Edition

013610066X, 9780136100669

More Books

Students also viewed these General Management questions

Question

22: Find the forecast for month 9 by using ES with = 0.3.

Answered: 1 week ago